Thailand will unlock $5.7 billion to modernise the MRO capabilities of U-Tapao |
Romain Guillot |
|
02 MAR 2017 | 99 words
|
|
|
|
The Thai development agency (BOI) revealed an investment plan of some $5.7 billion aimed at developing the MRO capacities at U-Tapao airport. The project comprises three phases that are spread out between 2017 and 2031.
The first phase (2017-2021) will allow the construction of a new maintenance hangar for Thai Airways. The second phase (2022-2026) will be devoted to the development of a new hub dedicated to the MRO.
The third phase will focus on the development of the country's industrial capababilities in aerospace. The two U-Tapao runways will be lengthened.
|
|
|